Estimation of Brickwork Foundation of Building(Bricks Calculation)

In this video, we are going to explain to you that how to calculate brickwork of foundation according to the drawing. after watching this video you will be able to learn Estimation of Brickwork Foundation of Building(Bricks Calculation)

In This article, we are going to study Bricks Calculation that is how to calculate the quantity of brickwork in the foundation of a building using AutoCAD. Brickwork Foundation is the foundation provided for the wall of the building. It is constructed below the plinth level i.e. Below the Ground Level. This foundation is made up of brick masonry.

Calculation of Quantity of Brickwork in foundation

For Bricks Calculation the quantity of brickwork in the foundation of a building, we have to first study and analyze the given drawing of foundation from both views i.e.

  1. Top view / Layout Plan
layout of brickwork foundation

Fig- 1 Foundation Layout Plan

In This Plan you will see that FW1 represents the area where brick work is done.

FW1- Foundation Wall 1

  • Cross section view
cross section of brickwork foundation

In this view you will see the foundation of 9 inch thick brick wall. The foundation is constructed in steps above PCC. There are 4 steps provided of various width and thickness.

To find out the Bricks Calculation, we have to first find out three things

  1. Length of the brick wall
  2. Width of the brick wall
  3. Depth/ Thickness of the brick wall

First we have to find the length of the wall, the length of the wall can be calculated by analysis the layout plan/ top view.

In top view of drawing we have to determine the length of the wall using AutoCAD.

See the figure below.

foundation details

Fig. 3

Now as you know the brickwork is done from column to column. So by using dimension command in autocad we find the distance between column to column and then we add all the distance.

In fig. you seen than the distance between the column of F1 footing and column of F3 footing is 10 feet 2 inch. And the distance between the column of F3 footing and F2 footing is 18 Feet 3 Inch. As shown in fig. 3

Similarly you will find all the Distance between Column to Column and add all the distance which is made our required length.

The complete length of the wall is 215.33 Feet

Now, to find out width and thickness of wall we have to study the cross section view , the width and thickness of each step is given in the drawing.

So all the three things i.e. Length, width, thickness are available now to find out the quantity of brick work

Step1- Calculate the Quantity of brickwork in step 1 which is just above the PCC

Length = 215.33 ft

Width=1ft 10.5inch= 1.875ft

Thickness= 6 inch = 0.5ft

 Quantity of brickwork for 1 step = length x Width x Depth

                                                           = 215.33 x 1.875 x 0.5

= 201.87 Cubic Feet 

=or it is Equal to 5.72 Cum

Step 2- Calculate the Quantity of brickwork in Step 2 which is just above Step 1

Length = 215.33 ft

Width=1ft 6 inch= 1.5ft

Thickness= 6 inch = 0.5ft

 Quantity of brickwork for 1 step = length x Width x Depth

                                                           = 215.33 x 1.5 x 0.5

= 161.49 Cubic Feet 

=or it is Equal to 4.577 Cum

Step 3- Calculate the Quantity of brickwork in Step 3 which is just above Step 2.

Length = 215.33 ft

Width=1ft 1.5 inch= 1.125ft

Thickness= 6 inch = 0.5ft

 Quantity of brickwork for 1 step = length x Width x Depth

                                                           = 215.33 x 1.125 x 0.5

= 121.12 Cubic Feet 

=or it is Equal to 3.433 Cum

Step 4- Calculate the Quantity of brickwork in Step 4 which is just above Step 3.

Length = 215.33 ft

Width   = 9 inch

Now in Step 4 You have to find the thickness/ depth because it is not given directly.

Thickness =(total depth above step 3 –depth of beam – dpc thickness)

= 4ft – 1ft 3 inch -2 inch

= 2.5834 ft

 Quantity of brickwork for 1 step = length x Width x Depth

                                                           = 215.33 x 0.75x 2.5834

= 417.21 Cubic Feet 

=or it is Equal to 11.825 Cum

Total quantity of brickwork of all the steps = (Step1 +Step2+Step3+ step4)

=(5.72+ 4.577 + 3.433 + 11.825)

=25.555 cum

Now, we have to calculate number of bricks in this quantity

According to Bureau of Indian Standards, 1 Cum of Brickwork Contain 500 Bricks

Therefore, 25.555 cum Quantity of brickwork contains

 = 25.555 x 500

= 12777.5 numbers of bricks

Given Below is the link for Building Estimation Course

Building Estimation Course